Questions 11–15

  1. 11foundation · easy

    During project execution, the project team is performing quality assurance activities as defined in the quality management plan. Which activity is an example of quality assurance?

    Select an answer first
  2. 12expert · hard

    A project manager is planning a new manufacturing facility. The client has requested that the facility be carbon-neutral, but the budget is tight. The project manager needs to integrate sustainability into quality planning while managing costs. What should the project manager do?

    Select an answer first
  3. 13expert · hard

    A project manager is working on a project to develop a new medical device. The device must comply with ISO 13485 (quality management for medical devices). The project sponsor wants to reduce costs by using a lower-cost supplier for a critical component. The supplier's quality history is unknown. What should the project manager do?

    Select an answer first
  4. 14application · medium

    A project manager is leading a software development project. The team has been conducting regular quality audits, and the latest audit found that the team is not following the defined coding standards. The project manager needs to address this issue. What should the project manager do?

    Select an answer first
  5. 15application · medium

    A software development project is in the execution phase. The project manager has implemented a quality management plan that includes code reviews and automated testing. During a quality audit, the team discovers that the automated tests are not covering a critical module, and several defects have been found in that module. What should the project manager do?

    Select an answer first