Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

Project Management Professional (PMP)

Domain 2Objective 5

Task 5 Plan and Manage Procurement PMP Practice Questions (Page 5)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 38 practice questions to prepare you well beyond it. (estimate)

38questions here
8free pages
10concepts
41%of the exam

Questions 21–25

  1. 21foundation · easy

    What is the primary goal of agreement negotiation?

    Select an answer first
  2. 22foundation · easy

    During the Control Procurements process, which activity verifies that the deliverables meet the acceptance criteria defined in the contract?

    Select an answer first
  3. 23foundation · easy

    Which factor is most important to consider when determining your negotiation strategy?

    Select an answer first
  4. 24foundation · easy

    Which document is a key input to developing the procurement strategy because it describes the project's overall approach to achieving its objectives?

    Select an answer first
  5. 25application · medium

    A vendor has completed all deliverables under a contract. The project manager needs to close the procurement. What is the first step in the closure process?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.