Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)
29questions here
6free pages
6concepts
31%of the exam
Questions 26–29
- 26
A project manager has obtained verbal approval from the sponsor and customer for the baseline schedule. However, the customer's representative is about to go on a long leave, and the project manager needs to finalize the baseline. What should the project manager do?
Select an answer first - 27
A project manager is establishing the PMB for a project. The organization has a standard process for setting baselines. What is the first step the project manager should take?
Select an answer first - 28
How is the Performance Measurement Baseline (PMB) used to enable performance measurement?
Select an answer first - 29
What does a positive schedule variance (SV) indicate when using the PMB for performance measurement?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.