Establish Baseline PMI-SP Practice Questions (Page 5)
Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)
29questions here
6free pages
6concepts
31%of the exam
Questions 21–25
- 21
A project manager has obtained verbal agreement from the sponsor and customer on the baseline schedule. What is the next step in the formal approval process?
Select an answer first - 22
A project manager is explaining the purpose of the Performance Measurement Baseline (PMB) to a new team member. Which statement accurately describes the PMB?
Select an answer first - 23
A project manager is establishing the Performance Measurement Baseline (PMB) for a new project. The PMB should include which of the following components?
Select an answer first - 24
A project manager has obtained sign-off on the baseline schedule from the sponsor and customer. What should the project manager do to ensure the baseline is properly established?
Select an answer first - 25
In the baseline schedule approval process, what is the primary role of the sponsor?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.