Task 1 Plan Risk Response PMI-RMP Practice Questions (Page 6)
Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
8concepts
13%of the exam
Questions 26–30
- 26
During risk response planning, the project team identifies a high-impact risk that can be completely eliminated by changing the project approach to use a proven technology instead of an experimental one. Which risk response strategy is being applied?
Select an answer first - 27
Which verbal communication technique is most effective for explaining the effectiveness of a risk response to non-technical stakeholders?
Select an answer first - 28
Which of the following best indicates that a risk response action has been effective?
Select an answer first - 29
A project team implemented a risk response to transfer the risk of currency fluctuation by entering into a forward contract. At the next risk review, the project manager wants to assess the effectiveness of this response. Which metric is most relevant?
Select an answer first - 30
In a RACI matrix, what does the 'A' stand for?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.