Task 1 Plan Risk Response PMI-RMP Practice Questions (Page 5)

Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)

30questions here
6free pages
8concepts
13%of the exam

Questions 21–25

  1. 21expert · medium

    A manufacturing project encounters an unplanned risk: a key machine breaks down and the spare part is not in stock. The lead time for the part is four weeks, but the project has a two-week deadline. The team identifies a local machine shop that can fabricate a replacement in one week, but at a high cost. The project manager must decide. What is the most appropriate workaround?

    Select an answer first
  2. 22application · medium

    A project manager needs to communicate to the steering committee that the mitigation response for a supply-chain risk has reduced the probability of delay from 60% to 20%. The committee is time-constrained and prefers visual summaries. Which communication method is most appropriate?

    Select an answer first
  3. 23application · medium

    During a network upgrade, a previously unidentified risk materializes: a critical switch fails and the team has no spare on hand. The project manager must restore service quickly. The procurement team says a replacement will take five days, but the project cannot afford more than two days of downtime. What is the most appropriate workaround?

    Select an answer first
  4. 24application · medium

    An IT project has an opportunity to deliver a new feature ahead of schedule if a beta version of a software library is used. The beta library is unstable, but the team has the expertise to fix issues quickly. The project sponsor is risk-averse but wants the early delivery. Which response strategy best exploits this opportunity?

    Select an answer first
  5. 25application · medium

    A software development project has a risk that a key third-party API will be deprecated mid-project. The team decides to mitigate by building an abstraction layer. The risk owner proposes the action: 'Monitor the API vendor's announcements and update the abstraction layer if needed.' Which improvement makes this action time-bound and assignable?

    Select an answer first