Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
5concepts
23%of the exam

Questions 21–23

  1. 21foundation · easy

    A project has a constraint that critical work cannot occur during a two-week holiday shutdown. How might this constraint affect the project schedule objective?

    Select an answer first
  2. 22application · medium

    During assumption and constraint analysis for a construction project, the team identifies the following items: (1) the soil condition at the site is stable, (2) the project must comply with local noise ordinances, (3) the supplier will deliver steel within four weeks, and (4) the site is in a flood zone. How should these items be categorized?

    Select an answer first
  3. 23application · medium

    A project to build a new office building has a constraint that construction cannot occur during the city's annual festival week. The project schedule currently places critical foundation work during that week. What is the most likely cascade effect on project objectives?

    Select an answer first
Finished these 3 questions?

Review the revealed explanations, or continue through the curriculum.