Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
5concepts
23%of the exam

Questions 16–20

  1. 16application · medium

    A project to organize a conference has a constraint that the venue must be booked at least six months in advance. The project team assumes the preferred venue will be available. What is the most likely cascade effect if the venue is already booked?

    Select an answer first
  2. 17foundation · easy

    Besides risk identification, the results of assumption and constraint analysis can also be used to inform which other project management process?

    Select an answer first
  3. 18expert · hard

    A project manager is leading a large infrastructure project. The assumptions log includes: (1) the government will approve the permit in 60 days, (2) the main contractor will have sufficient labor, and (3) the weather will be favorable for outdoor work. The constraint analysis shows the project must complete before the rainy season. During risk identification, the team discovers that the permit approval has been delayed to 120 days. What is the most critical cascade effect to assess?

    Select an answer first
  4. 19application · medium

    A project manager is updating the risk register after a constraint analysis revealed that a key regulatory approval is required before any construction can begin. The approval process is known to be unpredictable. How should this constraint be used in risk identification?

    Select an answer first
  5. 20application · medium

    During a risk workshop, a stakeholder challenges a documented constraint that the project must use a specific legacy technology. The stakeholder believes a newer technology would be more efficient. What should the project manager do?

    Select an answer first