Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
23%of the exam
Questions 26–27
- 26
A project has a risk threshold for 'cost overrun' set at '10% of budget'. The project sponsor believes this threshold is too high and wants to lower it to '5%' to catch issues earlier. However, the project manager notes that the project has a history of cost variances around 6-8% that are not problematic. What is the best action?
Select an answer first - 27
A project has a risk threshold for 'data breach impact' set at 'high'. The organization's security team reports that the threshold is too vague and wants to make it more specific. What should the project manager do?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.