Task 3 Document Risk Triggers and Thresholds Based on Context/environment PMI-RMP Practice Questions (Page 2)

Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)

27questions here
6free pages
5concepts
23%of the exam

Questions 6–10

  1. 6expert · hard

    A project has a risk threshold for 'schedule delay' set at 'more than 5 days'. The project manager receives new information that a critical vendor is likely to be late, but the delay is estimated at only 3 days. A stakeholder argues the threshold should be lowered to 'more than 2 days' to trigger earlier action. The project manager is concerned about creating false alarms. What is the best approach?

    Select an answer first
  2. 7foundation · easy

    What is the most appropriate action when updated risk data indicates that a previously established risk compliance threshold is no longer consistent with a new regulatory requirement?

    Select an answer first
  3. 8foundation · easy

    What is the primary purpose of empowering stakeholders to challenge existing risk thresholds?

    Select an answer first
  4. 9application · medium

    A software development project has a risk that 'a key developer may leave the company'. The project manager needs to document the impact of this risk. Which statement best describes the impact?

    Select an answer first
  5. 10application · medium

    A pharmaceutical company is running a clinical trial project. The risk register currently lists a risk of 'adverse patient reaction' with a threshold of 'any occurrence'. After reviewing updated safety data, the risk owner proposes changing the threshold to 'any serious adverse event'. What should the project manager do first?

    Select an answer first