  1. 26application · medium

    A BA is monitoring the quality of requirements by tracking the number of defects found during design reviews. The defect rate is below the established threshold, but the BA notices that the design team is spending an unusually long time reviewing each requirement. What should the BA conclude from this variance?

    Select an answer first
  2. 27application · medium

    During a project, the BA tracks the number of requirements that are changed after sign-off. The metric is trending upward, and the BA suspects that requirements are not being fully understood during elicitation. According to the performance monitoring process, what should the BA do first?

    Select an answer first
  3. 28expert · hard

    A BA is monitoring the performance of the requirements elicitation process. The metric 'number of requirements approved per week' is below target, but the 'number of stakeholder interviews conducted' is above target. The BA suspects that the interviews are not yielding quality requirements. What is the most appropriate next step?

    Select an answer first
  4. 29foundation · easy

    Which technique is commonly used to monitor business analysis performance against established metrics?

    Select an answer first
Finished these 4 questions?

Review the revealed explanations, or continue through the curriculum.