Monitor and Control Program Performance PGMP Practice Questions (Page 3)

Part of the Governance domain, which accounts for 14% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 20 practice questions to prepare you well beyond it. (estimate)

20questions here
4free pages
4concepts
14%of the exam

Questions 11–15

  1. 11expert · hard

    A program manager is reviewing the program's KPIs and notices that the compliance KPI is green, but the stakeholder satisfaction KPI is red. The program is meeting all regulatory requirements, but stakeholders are dissatisfied with the program's communication. The program manager has analyzed the data in the PMIS and found that stakeholders are not receiving timely updates. What should the program manager do?

    Select an answer first
  2. 12foundation · easy

    A program manager is defining key performance indicators (KPIs) to monitor program benefits. Which KPI category would directly measure the degree to which program outputs are meeting stakeholder expectations?

    Select an answer first
  3. 13application · medium

    A program manager is preparing for the quarterly governance board review. During the last quarter, a new regulatory requirement was introduced that could affect the program's strategic objectives. The program manager has already assessed the impact and identified potential responses. What should the program manager do to ensure the governance board can make an informed decision?

    Select an answer first
  4. 14foundation · easy

    Which of the following is a primary purpose of a Program Management Information System (PMIS)?

    Select an answer first
  5. 15expert · hard

    A program manager is leading a program that is nearing a critical milestone. During a routine risk review, a new risk is identified that could cause a two-month delay and require additional funding. The governance board is not scheduled to meet for another six weeks. The program manager has already assessed the risk and developed a response that would cost $500,000 and reduce the delay to two weeks. What should the program manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.