Monitor and Control Program Performance PGMP Practice Questions (Page 1)

Part of the Governance domain, which accounts for 14% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 20 practice questions to prepare you well beyond it. (estimate)

20questions here
4free pages
4concepts
14%of the exam

Questions 1–5

  1. 1foundation · easy

    During program monitoring, a program manager wants to track the effectiveness of risk responses and the overall risk exposure. Which KPI category should be used?

    Select an answer first
  2. 2application · medium

    A program manager is establishing escalation policies for a large, multi-phase program. The program has a governance structure with component project managers, a program management office (PMO), and a steering committee. A project manager has identified a risk that could delay a component project by two weeks, but the delay would not affect the overall program benefits. According to the escalation policy, where should this risk be escalated?

    Select an answer first
  3. 3expert · hard

    A program manager is reviewing the program's KPIs and notices that the financial KPI is green, but the risk KPI is red. The risk KPI is based on the number of open high-impact risks. The program manager has identified that the risk KPI is not aligned with the program's risk appetite, which allows for a certain number of high-impact risks to be actively managed. What should the program manager do?

    Select an answer first
  4. 4application · medium

    A program manager is reviewing the program's KPIs and notices that the financial KPI is green, but the quality KPI is yellow. The program is delivering benefits as planned, but there is a trend of increasing defects in one component. What should the program manager do?

    Select an answer first
  5. 5application · medium

    A program manager is configuring the PMIS for a program with multiple stakeholders, including the governance board, component project managers, and external vendors. The program manager needs to ensure that sensitive financial information is only accessible to authorized stakeholders. What should the program manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.