PMIProgram Management Professional (PgMP)
Domain 5Objective 1
Establish Governance Framework PGMP Practice Questions (Page 2)
Part of the Governance domain, which accounts for 14% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)
23questions here
5free pages
3concepts
14%of the exam
Questions 6–10
- 6
A program manager is establishing governance for a program that spans multiple business units with conflicting priorities. The organization's governance structure includes a program board with representatives from each business unit. The program manager needs to ensure that the governance framework supports decision-making that balances these conflicting priorities. What should the program manager do?
Select an answer first - 7
A program manager is preparing for a stage gate review where the program has experienced significant cost overruns. The governance board needs to decide whether to continue funding the program. The program manager must present information that supports a transparent decision. What should the program manager do?
Select an answer first - 8
A program manager is defining governance standards for a program that will be implemented in phases. Each phase has different resource requirements and risk profiles. The program manager needs to ensure that governance standards are consistent yet adaptable to each phase. What should the program manager do?
Select an answer first - 9
A program manager is preparing for a stage gate review to obtain approval for the program's initiation phase. The governance board has asked for a presentation that justifies the program's business case and alignment with organizational strategy. What should the program manager present?
Select an answer first - 10
A global retail company is launching a program to unify its e-commerce platforms across three regions. Each regional IT department currently uses its own project management methodology, financial reporting format, and toolset. The program manager needs to establish a consistent governance approach that supports efficient decision-making and reporting to the executive steering committee. What should the program manager do first?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.