Part of the Strategic Program Alignment domain, which accounts for 15% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 4–6 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
6concepts
15%of the exam
Questions 21–25
- 21
A program manager has established the baseline for a program, but during execution, a major change in the organization's strategy occurs. The change affects the program's scope and financial framework. What should the program manager do?
Select an answer first - 22
What is the primary purpose of developing a high-level program roadmap with milestones and preliminary estimates?
Select an answer first - 23
How are financial and nonfinancial estimates used in program funding authorization?
Select an answer first - 24
Which of the following is an example of a nonfinancial benefit?
Select an answer first - 25
A program manager has drafted a high-level roadmap for a new regulatory compliance program. The executive sponsor is concerned about the program's alignment with the organization's strategic goals. What should the program manager do to gain the sponsor's approval?
Select an answer first