Part of the Understand how to apply and tailor relevant aspects of PRINCE2 practices in context domain, which accounts for 51% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~31–51 in this domain), expect 4–7 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
5concepts
51%of the exam

Questions 21–24

  1. 21application · medium

    During a project, a team manager reports that a work package is likely to exceed its time tolerance by five days. The project manager reviews the situation and determines that the stage tolerance will still be met. According to PRINCE2, what should the project manager do?

    Select an answer first
  2. 22application · medium

    A project manager is monitoring progress against the stage plan. The stage plan has a baseline with a cost tolerance of ±10%. The project manager receives a checkpoint report from the team manager indicating that the work package is 5% over budget. The project manager assesses that the stage is still within tolerance. What should the project manager do?

    Select an answer first
  3. 23expert · hard

    A project manager is tailoring the progress practice for a project that is being delivered using an agile approach. The project has a product owner who is responsible for prioritizing the backlog, and the team works in sprints. The project board is concerned about the lack of traditional progress reports. What is the most appropriate way to adapt the progress practice?

    Select an answer first
  4. 24expert · hard

    A project manager is tailoring the progress practice for a project that is part of a larger program. The program office requires a standardized highlight report format and a monthly reporting cycle. However, the project is a high-risk, fast-moving initiative that would benefit from more frequent reporting. What is the most appropriate approach?

    Select an answer first