3.5 Risk PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 1)
Part of the Understand how to apply and tailor relevant aspects of PRINCE2 practices in context domain, which accounts for 51% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~31–51 in this domain), expect 4–7 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
Questions 1–5
- 1
Which of the following is a criterion for evaluating the effectiveness of the risk practice?
Select an answer first - 2
A multinational project involves multiple regulatory environments. The project manager needs to ensure that risk management complies with local regulations while maintaining a consistent approach across the project. What is the most appropriate way to tailor the risk practice?
Select an answer first - 3
A project manager is assessing a risk that could delay the project by two weeks if it occurs. The probability is rated as 'likely' and the impact as 'major' on the organization's 5x5 risk matrix. The project manager wants to prioritize this risk against others. What is the most appropriate next step in the risk management procedure?
Select an answer first - 4
A project manager needs to communicate a newly identified risk to the project board. The risk is not yet fully assessed. What is the most appropriate way to communicate this risk?
Select an answer first - 5
When tailoring the risk practice for a small, low-complexity project, what is the most appropriate approach?
Select an answer first
Review the revealed explanations, or continue through the curriculum.