
MSP Practitioner (5th edition)
Domain 2Objective 4
2.4 Justification Theme (chapter 6) MSP-PRACTITIONER-5TH-EDITION Practice Questions (Page 4)
Part of the Understand how to apply and tailor relevant aspects of the MSP themes in context domain, which makes up ~39% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~23–39 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
8concepts
Questions 16–20
- 16
A programme has identified two risks: a regulatory risk that new legislation will increase compliance costs, and a market risk that a competitor will launch a similar product. The risks are assessed as having a 30% and 40% probability, with impacts of £1 million and £2 million respectively. The risk manager notes that if the regulatory risk materializes, the competitor's product launch becomes more likely. What is the most appropriate way to assess the combined effect of these risks on the business case?
Select an answer first - 17
A programme is mid-way through its delivery phase. The Programme Manager notices that the actual spend on a workstream is consistently 10% above the budgeted amount, but the overall programme spend is within tolerance. The financial plan includes a contingency fund for risks. What should the Programme Manager do?
Select an answer first - 18
A programme's justification approach includes a business case that is updated only at the end of each tranche. The programme is in a rapidly changing market, and the SRO is concerned that the business case may become outdated between tranches. What is the most effective way to ensure the justification approach remains fit for purpose?
Select an answer first - 19
What is a disbenefit in the context of the justification theme?
Select an answer first - 20
A programme's financial plan includes a budget of £10 million, with a contingency of £1 million. The programme is in its second year, and the actual spend is £6 million, which is £1 million over the forecast for this point. The Programme Manager identifies that the overspend is due to a delay in a dependency that has increased costs. What should the Programme Manager do?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “MSP-PRACTITIONER-5TH-EDITION” is a trademark of its owner, used for identification only.