Part of the Understand how to apply and tailor relevant aspects of the MSP themes in context domain, which makes up ~39% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~23–39 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
9concepts
Questions 1–5
- 1
A programme is delivering a new customer portal. The portal's go-live depends on a new API being released by an external vendor. The vendor has a history of late delivery. The programme manager has recorded this dependency in the delivery plan. What is the most effective way to manage this dependency?
Select an answer first - 2
A programme manager is establishing the structure theme for a new programme. The programme board has appointed a business change manager and a programme office. The programme manager needs to clarify who is responsible for ensuring that the delivery plan is created and maintained. According to the structure theme, which role has this area of focus?
Select an answer first - 3
Why is multimodal delivery applied within the structure theme?
Select an answer first - 4
A public-sector programme is modernizing citizen services. One work stream will replace a legacy benefits system with a commercial off-the-shelf product, while another will develop a new mobile app using an agile approach with frequent releases. The programme board is concerned that a single, uniform delivery method will not suit both work streams. The programme manager proposes multimodal delivery. Which statement best describes how the programme manager should apply this concept?
Select an answer first - 5
A programme is introducing a new online self-service portal for a utility company. The business case identifies reduced call-center volume as a key benefit. The programme manager is developing the benefits realization plan and needs to decide when and how this benefit will be measured. Which content should the benefits realization plan include?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “MSP-PRACTITIONER-5TH-EDITION” is a trademark of its owner, used for identification only.