Part of the Business Environment domain, which accounts for 26% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~23–40 in this domain), expect 3–5 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
7concepts
26%of the exam
Questions 31–32
- 31
A construction project is underway, and the project manager has identified a risk of severe weather delaying the foundation work. The team implemented a response to monitor weather forecasts and have contingency plans ready. Two weeks later, the project manager reviews the risk register and notices that the risk status is still 'open' and the response is marked as 'in progress'. What should the project manager do next?
Select an answer first - 32
Which component of the risk management plan defines the specific individuals who will be responsible for each risk management activity?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.