A project manager is quantifying contingency for a project with two risks: Risk A has a 50% probability of causing a $100,000 cost overrun, and Risk B has a 10% probability of causing a $500,000 cost overrun. The project has a total budget of $1 million. The sponsor wants to minimize the contingency amount but also wants to avoid a high probability of exceeding the budget. What is the most appropriate contingency amount?
Select an answer first - 7
What is the purpose of allocating contingency funds to specific risks or work packages?
Select an answer first - 8
A project manager is developing a spend tracking plan for a 12-month project with a budget of $1.2 million. The finance department requires monthly reports, but the project sponsor wants to know about any cost overrun within two weeks. The project team has a mix of internal and external resources. What is the most appropriate spend tracking approach?
Select an answer first - 9
Which tool or technique is commonly used to quantify risks for contingency reserve estimation?
Select an answer first - 10
What is the purpose of a financial reporting plan?
Select an answer first