Questions 6–10
- 6
What is the primary role of a project manager in representing the 'voice of the team'?
Select an answer first - 7
Which tool is commonly used to clarify roles and responsibilities in a project?
Select an answer first - 8
During a project status meeting, a team member reports a significant issue: a critical vendor will be late in delivering a key component, which will delay the project by at least three weeks. The project manager wants to resolve this collaboratively with the team. What is the first step the project manager should take in applying a structured problem-solving process?
Select an answer first - 9
Which action best demonstrates team empowerment by a project manager?
Select an answer first - 10
A project manager is leading a project that is behind schedule. The team has identified a way to recover the schedule by working overtime for the next four weeks. However, the project manager is concerned about team burnout and the potential for decreased quality. The project sponsor has stated that the schedule is the top priority. The project manager must balance the sponsor's priority with the team's well-being. What is the most effective course of action?
Select an answer first