Questions 6–10
- 6
A project has well-defined requirements and a stable scope. Which development approach is MOST appropriate?
Select an answer first - 7
During a review of the integrated project management plan, the project manager notices that the procurement plan assumes a vendor deliverable that is not reflected in the schedule. What should the project manager do?
Select an answer first - 8
A project manager is planning a global rollout of a new software system. The project has a fixed budget and a tight timeline. The team is distributed across multiple time zones. What execution strategy should the project manager recommend?
Select an answer first - 9
A project manager receives a change request that will affect the project's scope and schedule baseline. The change is approved by the change control board (CCB). What should the project manager do next?
Select an answer first - 10
Why should the integrated project management plan be maintained throughout the project?
Select an answer first