PMIScheduling Professional (PMI-SP)

Domain 5Objective 2

Task 2 Generate and Maintain Visibility of Project Schedule, by Working with the Project Manager And/or Stakeholders, in Order to Maintain Stakeholder Support. PMI-SP Practice Questions (Page 2)

Part of the Stakeholder Communications Management domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 35 practice questions to prepare you well beyond it. (estimate)

35questions here
7free pages
8concepts
14%of the exam

Questions 6–10

  1. 6expert · hard

    A project scheduler is working with a project manager who prefers to communicate schedule changes only during monthly status meetings. However, stakeholders have expressed a need for more frequent updates, especially during a period of high uncertainty. The scheduler must balance the project manager's preference with stakeholder needs. What should the scheduler do?

    Select an answer first
  2. 7expert · hard

    A project scheduler is identifying stakeholders for schedule visibility on a project that involves multiple departments, each with different priorities. The scheduler has limited resources and cannot provide detailed schedule reports to everyone. The scheduler must prioritize which stakeholders receive detailed reports. What should the scheduler do?

    Select an answer first
  3. 8foundation · easy

    Which of the following is an example of a schedule update mechanism?

    Select an answer first
  4. 9expert · hard

    A project scheduler has implemented a new dashboard for schedule visibility. After a few weeks, the scheduler notices that some stakeholders are not using the dashboard and continue to ask for emailed reports. The scheduler must decide whether to continue the dashboard, revert to email, or use both. What should the scheduler do?

    Select an answer first
  5. 10application · medium

    A project scheduler is starting a new project and needs to identify which stakeholders require schedule visibility. The project has a diverse set of stakeholders, including a regulatory agency, an internal IT team, and a customer representative. The scheduler must determine what information each stakeholder needs. What should the scheduler do first?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.