Task 4 Communicate Schedule Issues That Could Impact Delivery of Project Scope or Adherence to the Schedule Management Plan, in Order to Elevate Awareness to Relevant Stakeholders. PMI-SP Practice Questions (Page 2)

Part of the Stakeholder Communications Management domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)

22questions here
5free pages
4concepts
14%of the exam

Questions 6–10

  1. 6foundation · easy

    Which of the following best describes a schedule issue that should be identified for communication?

    Select an answer first
  2. 7foundation · easy

    When a schedule issue is identified, what is the first step in assessing its impact?

    Select an answer first
  3. 8application · medium

    A marketing campaign project is behind schedule because the creative team is waiting for final brand guidelines from the client. The project manager needs to communicate this issue to stakeholders. Which communication approach is most appropriate?

    Select an answer first
  4. 9expert · hard

    A large infrastructure project is facing a schedule delay due to a permit approval issue. The project manager must communicate this to stakeholders. The project sponsor is highly influential but has low interest in day-to-day details. The permit officer has high interest but low influence. The project team has high interest and moderate influence. How should the project manager prioritize communication?

    Select an answer first
  5. 10application · medium

    A software development project is running two weeks behind schedule due to an unexpected technical debt. The project manager must communicate this issue. Which stakeholders should receive the communication about the schedule delay?

    Select an answer first