Part of the Risk Analysis domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 7–12 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)
22questions here
5free pages
4concepts
23%of the exam
Questions 16–20
- 16
A project manager wants to encourage team members to identify risks independently. The team is distributed across multiple time zones and has varying levels of risk management experience. What is the most effective way to empower them?
Select an answer first - 17
A project manager is leading a project with a team that is highly experienced but has a culture of not reporting risks because they are seen as a sign of failure. The project manager wants to change this culture and empower the team to identify risks independently. What is the most effective first step?
Select an answer first - 18
A project manager is leading a cross-functional team that includes members from engineering, marketing, and finance. The team has never worked together before. The project manager wants to empower them to identify risks independently. What is the best way to create a supportive environment?
Select an answer first - 19
A construction project has identified a risk that a key supplier may deliver steel beams two weeks late. The project has a tight schedule with a penalty clause for late completion. The project manager is analyzing the impact of this risk. Which analysis best captures the impact on project objectives?
Select an answer first - 20
A multinational corporation is planning a data center migration. The project must comply with data residency regulations in three countries, each with different requirements. The company's strategic objective is to reduce operational costs by consolidating data centers. The project manager is assessing risk complexity. The migration involves interdependent workstreams: network reconfiguration, data transfer, and application re-platforming. The project manager has limited budget for risk analysis. What is the most appropriate approach to assess the risk complexity?
Select an answer first