Questions 21–25
- 21
A business analyst is planning solution evaluation for a project that will implement a new customer onboarding process. The business goal is to reduce onboarding time by 30%. Which evaluation approach should the BA include in the plan?
Select an answer first - 22
Which of the following best describes the purpose of planning the business analysis approach?
Select an answer first - 23
A business analyst is planning stakeholder engagement for a project with a high-profile sponsor who is very busy and a group of end users who are resistant to change. The BA needs to ensure requirements are well understood. What is the best engagement strategy?
Select an answer first - 24
What is the purpose of planning traceability?
Select an answer first - 25
A business analyst is planning stakeholder identification for a project that will introduce a new customer relationship management (CRM) system. The project will affect sales, marketing, customer support, and IT. The BA has identified the sales director as a key stakeholder. Which additional stakeholder group should the BA include to ensure comprehensive coverage?
Select an answer first