Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

Certified Associate in Project Management

Domain 1Objective 4

Task 4 Determine How to Follow and Execute Planned Strategies or Frameworks (e.g., Communication, Risks, Etc.). CAPM Practice Questions (Page 2)

Part of the Project Management Fundamentals and Core Concepts domain, which accounts for 36% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~25–43 in this domain), expect 5–9 from this objective — we provide 16 practice questions to prepare you well beyond it. (estimate)

16questions here
4free pages
3concepts
36%of the exam

Questions 6–10

  1. 6application · medium

    A project manager is initiating a project to build a new warehouse. The project sponsor asks the project manager to identify the key stakeholders and document their expectations. Which activity is the project manager performing?

    Select an answer first
  2. 7application · medium

    A project manager is working on a project to implement a new inventory system. The business case identifies cost savings as a key benefit. During planning, the project manager documents how these savings will be measured and when they will be realized. Which document is the project manager creating?

    Select an answer first
  3. 8application · medium

    A project manager is preparing to start a new project. The project sponsor has not yet signed the project charter. The project manager has identified stakeholders and started to develop the project management plan. What should the project manager do first?

    Select an answer first
  4. 9application · medium

    A project manager is planning a project to reduce customer churn. The business case states that the project will increase customer retention by 10% within one year. The project manager includes this metric in the benefits management plan. What is the primary purpose of documenting this metric?

    Select an answer first
  5. 10application · medium

    A project manager is executing a project to launch a new mobile app. The communication plan specifies that the project sponsor receives a weekly dashboard. The project manager notices that the sponsor has not opened the dashboard for two weeks. What should the project manager do?

    Select an answer first