Part of the Predictive, Plan-Based Methodologies domain, which accounts for 17% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~12–20 in this domain), expect 4–7 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
11concepts
17%of the exam
Questions 26–30
- 26
If a project has an Earned Value (EV) of $40,000 and a Planned Value (PV) of $50,000, what is the Schedule Performance Index (SPI)?
Select an answer first - 27
What does a negative Schedule Variance (SV) indicate in earned value management?
Select an answer first - 28
Which of the following is a characteristic of a work package?
Select an answer first - 29
Given a project network with two paths—Path A: 3+5+2=10 days and Path B: 4+4+4=12 days—which path is critical?
Select an answer first - 30
A project manager is analyzing a network diagram. Activity X has an early start of day 5, a late start of day 9, an early finish of day 12, and a late finish of day 16. The project manager needs to know how much the activity can slip without delaying the project. What should the project manager calculate?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to CAPM
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “CAPM” is a trademark of its owner, used for identification only.