Part of the Predictive, Plan-Based Methodologies domain, which accounts for 17% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~12–20 in this domain), expect 4–7 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
11concepts
17%of the exam
Questions 16–20
- 16
A project is experiencing schedule variance, and multiple work streams are making conflicting changes to recover. The project manager needs to ensure the changes are coordinated. What should the project manager do?
Select an answer first - 17
What is the primary purpose of the integration management plan?
Select an answer first - 18
Using the Critical Path Method, what is the minimum duration of a project if the critical path consists of three activities with durations of 5, 7, and 4 days?
Select an answer first - 19
A software project has three paths: Path 1 (Design → Code → Test) = 30 days, Path 2 (Design → Code → Integration) = 26 days, and Path 3 (Design → Documentation → Review) = 22 days. The project manager wants to identify which activities are critical. Which activities should be flagged?
Select an answer first - 20
What is the primary purpose of the quality management plan?
Select an answer first