Certified Associate in Project Management
Domain 2Objective 2
Task 2 Demonstrate an Understanding of a Project Management Plan Schedule. CAPM Practice Questions (Page 2)
Part of the Predictive, Plan-Based Methodologies domain, which accounts for 17% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~12–20 in this domain), expect 4–7 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
11concepts
17%of the exam
Questions 6–10
- 6
Which process is part of project integration management?
Select an answer first - 7
A construction project has four paths through its network diagram. Path A takes 42 days, Path B takes 38 days, Path C takes 45 days, and Path D takes 40 days. The project sponsor asks the project manager for the earliest date the project can be completed. What should the project manager report?
Select an answer first - 8
What does a Schedule Performance Index (SPI) of 0.8 indicate?
Select an answer first - 9
In a project network diagram, which activities are considered critical?
Select an answer first - 10
What is the primary purpose of a Work Breakdown Structure (WBS)?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “CAPM” is a trademark of its owner, used for identification only.