Part of the Understand the PRINCE2 processes and how they are carried out throughout the project domain, which accounts for 15% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~4–6 in this domain), expect 1–2 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)
24questions here
5free pages
7concepts
15%of the exam
Questions 21–24
- 21
Which document is created during the Initiating a Project process?
Select an answer first - 22
A project has been authorized by the project board. The project manager has received approval of the project brief and is now ready to establish the project's foundation. What should the project manager do next?
Select an answer first - 23
Which document is produced during the Closing a Project process?
Select an answer first - 24
What is the primary purpose of the Managing a Stage Boundary process?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PRINCE2-FOUNDATION-VERSION-7
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.