Part of the Understand the PRINCE2 processes and how they are carried out throughout the project domain, which accounts for 15% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~4–6 in this domain), expect 1–2 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)
24questions here
5free pages
7concepts
15%of the exam
Questions 16–20
- 16
A team manager has accepted a work package and is now executing it. The team manager needs to report progress to the project manager. What should the team manager do?
Select an answer first - 17
Which activity is performed in the Controlling a Stage process?
Select an answer first - 18
Which activity is part of the Directing a Project process?
Select an answer first - 19
A team manager has received a work package from the project manager. The work package specifies the products to be created and the acceptance criteria. What should the team manager do to ensure the products are delivered according to specifications?
Select an answer first - 20
A project is nearing the end of a stage. The project manager needs to review the stage results, update the project plan, and prepare for the next stage. What should the project manager do?
Select an answer first