- 26
A test manager and a client are in a dispute over whether a set of test results meets the acceptance criteria. The contract specifies a dispute resolution process that includes negotiation, then mediation, then arbitration. Negotiation has failed. What is the most appropriate next step?
Select an answer first - 27
What is the primary purpose of monitoring contract compliance?
Select an answer first - 28
What is the first step in an effective change control process for a test contract?
Select an answer first - 29
A test manager is working under a contract that includes a change control board (CCB). The client requests a change to the test schedule that will delay the delivery of a key deliverable. What is the most appropriate action?
Select an answer first - 30
A test manager is managing a fixed-price contract for a test phase. The client requests a change that will increase the test effort by 20%. The contract includes a change control process but does not specify how the price will be adjusted. What is the most appropriate action?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to CTEL-TM-OTM
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by ISTQB. “CTEL-TM-OTM” is a trademark of its owner, used for identification only.