Questions 6–10
- 6
In a fixed-price test contract, which statement best describes the financial risk allocation between the buyer and the provider?
Select an answer first - 7
A test manager and a client are in a dispute over the ownership of test artifacts. The contract is silent on this issue. The client claims ownership of all test artifacts, while the test manager believes the supplier retains ownership of the test approach and tools. What is the most appropriate first step?
Select an answer first - 8
What is a common contractual risk in a time-and-materials test contract?
Select an answer first - 9
A test manager is monitoring a contract with a test tool vendor. The contract includes an SLA for tool uptime of 99.5%. The vendor has reported 99.2% uptime for the last quarter. What is the most appropriate action?
Select an answer first - 10
During contract negotiation for a test automation project, the client wants to include a clause that requires the test automation scripts to be delivered as a deliverable. The test manager is concerned about the maintainability of the scripts. What is the most important negotiation point to clarify?
Select an answer first