Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
4concepts
33%of the exam
Questions 11–15
- 11
A project manager is planning the rollout of a new customer relationship management (CRM) system. The team must first migrate customer data from the legacy system, then configure the new CRM, and finally train the sales team. The project manager needs to document the order in which these activities must occur to establish the project's workflow. Which document should the project manager create?
Select an answer first - 12
A project manager is leading a mobile app launch. The project sponsor has requested a high-level schedule that shows only the most important dates, such as the completion of the beta version, the start of the marketing campaign, and the public release. Which scheduling element should the project manager provide to the sponsor?
Select an answer first - 13
In a project schedule, activity B cannot start until activity A is completed. Which of the following BEST describes the relationship between activities A and B?
Select an answer first - 14
A project manager is reviewing the project schedule. The project has a milestone 'Phase 1 Complete' scheduled for Friday. The team has completed all the work for Phase 1, but the project manager has not yet verified that all deliverables meet the quality standards. What should the project manager do to maintain an accurate schedule?
Select an answer first - 15
A project manager is planning the construction of a new office building. The activity 'Pour Foundation' cannot start until 'Excavate Site' is complete. The project manager has estimated that 'Excavate Site' will take 5 days and 'Pour Foundation' will take 3 days. What type of dependency exists between these two activities?
Select an answer first