Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)

19questions here
4free pages
4concepts
33%of the exam

Questions 6–10

  1. 6application · medium

    A project manager is managing a website redesign project. The team has just completed the 'Content Creation' activity, which was a predecessor to 'Website Development'. The project manager has received a change request to add a new 'Legal Review' activity that must be completed before 'Website Development' can begin. What is the project manager's first action to keep the schedule accurate?

    Select an answer first
  2. 7application · medium

    A project manager is developing a schedule for a marketing campaign. The team has estimated that the 'Design Ad' activity will require 40 hours of a graphic designer's time. The graphic designer is available for 20 hours per week. What is the duration of the 'Design Ad' activity?

    Select an answer first
  3. 8expert · hard

    A project manager is planning a construction project. The activities are 'Lay Foundation' (5 days), 'Build Walls' (10 days), and 'Install Roof' (4 days). 'Build Walls' cannot start until 'Lay Foundation' is complete. 'Install Roof' cannot start until 'Build Walls' is complete. The project manager has two teams available. Team A can do 'Lay Foundation' and 'Install Roof'. Team B can do 'Build Walls'. What is the minimum duration of the project?

    Select an answer first
  4. 9foundation · easy

    A project manager is reviewing the project schedule and finds that a task took longer than planned, which will affect the project end date. What should the project manager do to address this situation?

    Select an answer first
  5. 10application · easy

    A project manager is estimating the resources for a training project. The project requires a trainer for 3 days and a training room for 3 days. The trainer is also needed for 1 day of preparation before the training. What is the total resource requirement for the trainer?

    Select an answer first