Part of the Project life cycle phases domain, which accounts for 30% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~11–18 in this domain), expect 2–4 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
6concepts
30%of the exam

Questions 11–15

  1. 11application · medium

    A project team is in the execution phase, and a key stakeholder is unhappy with the project's progress. The stakeholder is threatening to withdraw support. The project manager needs to address the stakeholder's concerns. What should the project manager do?

    Select an answer first
  2. 12expert · hard

    A project manager is executing a project and a vendor is demanding more money to complete the work, claiming the scope has changed. The project manager disagrees and believes the vendor is trying to exploit the situation. The project is already over budget. What should the project manager do?

    Select an answer first
  3. 13expert · hard

    A project manager is executing a project and the vendor has submitted an invoice that includes charges for work that was not authorized. The project manager needs to address this without delaying the project. What should the project manager do?

    Select an answer first
  4. 14expert · hard

    A project manager is executing a project and discovers that a key team member has been padding their timesheet, causing the budget to be overstated. The team member is a top performer and the project is behind schedule. What should the project manager do?

    Select an answer first
  5. 15application · medium

    During a project status meeting, two team leads begin arguing about the technical approach for an upcoming deliverable. The project manager needs to keep the meeting productive and resolve the conflict. What should the project manager do?

    Select an answer first