Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)
33questions here
7free pages
7concepts
33%of the exam
Questions 11–15
- 11
A project manager is closing a project that had a significant issue with a data migration that was resolved after several attempts. The project manager wants to document the outcome for future reference. What is the MOST valuable information to include in the lessons learned?
Select an answer first - 12
A project team is using a shared spreadsheet to track issues. The project manager notices that team members are overwriting each other's updates, and the status of several issues is now inaccurate. The project manager needs a more reliable method that also provides a clear audit trail. Which action should the project manager take?
Select an answer first - 13
A project manager is managing a project where a key stakeholder has requested daily updates on a specific issue. The project manager has been providing updates via email. The stakeholder is now requesting a more immediate method. What should the project manager do?
Select an answer first - 14
During a marketing campaign project, a team member reports that a graphic designer has been consistently late in delivering assets. This has not yet affected the schedule, but the project manager is concerned. How should the project manager categorize this issue?
Select an answer first - 15
A key vendor informs the project manager that a critical component will be delayed by three weeks. The project team has identified a substitute component from another vendor that is available immediately but costs 15% more. The project has a small budget reserve. What is the most appropriate resolution technique for the project manager to use?
Select an answer first