Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
33%of the exam
Questions 11–15
- 11
In a Waterfall project, which communication method is typically used to formally report progress against the project plan at regular intervals?
Select an answer first - 12
A company is developing a new customer relationship management (CRM) system. The sales team has conflicting opinions on features, and the executive sponsor insists on seeing a working prototype within 60 days. The IT department, however, has a history of failed projects due to unclear requirements and wants a detailed specification before any coding begins. The project manager must choose an approach that satisfies both the sponsor's deadline and the IT department's concern. Which approach best balances these constraints?
Select an answer first - 13
A startup is building a minimum viable product (MVP) with a team of five developers and one designer. The CEO wants to be deeply involved in prioritizing features but has no time to attend daily meetings. Which Agile role should be assigned to the CEO, and how should the team handle the CEO's limited availability?
Select an answer first - 14
A marketing agency is developing a website for a client who wants to see the design evolve and provide feedback after each major section is built. The client cannot commit to a final design until they see it in a browser. The project has a flexible timeline but a strict budget cap. Which methodology and communication cadence should the agency choose?
Select an answer first - 15
An Agile team is struggling because the product owner is also the sales director and frequently misses sprint reviews due to client meetings. The development team completes features but discovers at the end of the sprint that the priorities have changed. The scrum master needs to improve the flow of requirements without adding overhead. Which action should the scrum master take?
Select an answer first