Project Management Professional (PMP)
Domain 1Objective 5
Task 5 Align Stakeholder Expectations PMP Practice Questions (Page 5)
Part of the People domain, which accounts for 33% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~30–51 in this domain), expect 4–6 from this objective — we provide 25 practice questions to prepare you well beyond it. (estimate)
25questions here
5free pages
5concepts
33%of the exam
Questions 21–25
- 21
A project manager is starting a project to implement a new human resources system. The HR director expects the system to automate performance reviews, while the IT director expects minimal impact on existing infrastructure. The project manager needs to gather and document these expectations. Which technique is most effective?
Select an answer first - 22
A project manager is leading a software upgrade that affects several departments. The IT director has high power and high interest, the finance manager has high power but low interest, the end users have low power but high interest, and the compliance officer has low power and low interest. The project manager has limited time for stakeholder engagement. Which stakeholder should receive the most proactive engagement?
Select an answer first - 23
A project manager is initiating a project to upgrade the company's customer relationship management (CRM) system. The sales director expects the new system to include advanced analytics, while the IT director expects minimal integration effort. The project manager needs to document these expectations. Which technique is most appropriate?
Select an answer first - 24
A junior project coordinator struggles to communicate technical requirements to non-technical stakeholders, causing misunderstandings. The project manager wants to improve the coordinator's skills and better align stakeholder expectations. Which action best addresses this?
Select an answer first - 25
A project manager wants to implement a mentoring program to help team members develop skills for aligning stakeholder expectations. Which activity is most aligned with this goal?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.