Task 4 Establish Risk Management Strategy PMI-RMP Practice Questions (Page 2)
Part of the Risk Strategy and Planning domain, which accounts for 22% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~20–34 in this domain), expect 3–6 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)
31questions here
7free pages
7concepts
22%of the exam
Questions 6–10
- 6
Which metric is used to measure the effectiveness of risk responses?
Select an answer first - 7
A large enterprise is launching a multi-year infrastructure program. The program director wants risk management to be integrated into existing stage-gate reviews rather than run as a separate process. The risk manager must design a process that aligns with the organization's decision cadence. What should the risk manager do first?
Select an answer first - 8
A risk manager is establishing a risk management strategy for a new product development project. The project sponsor wants to track whether risk responses are actually reducing the likelihood and impact of key risks. Which metric should the risk manager define to directly measure this?
Select an answer first - 9
What is a key characteristic of a risk-aware culture fostered by servant leadership?
Select an answer first - 10
Which of the following is an example of an external risk category?
Select an answer first