Part of the Identify Business Needs and Solutions domain, which accounts for 26% of the PMI-CPMAI exam. PMI does not publish an official question count, but from its 160-minute exam (~65–105 total, ~17–27 in this domain), expect 2–3 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
9concepts
26%of the exam
Questions 21–25
- 21
A project manager is creating a timeline for an AI project. The model training phase cannot start until the data preparation phase is complete. What is this type of dependency called?
Select an answer first - 22
A healthcare startup is developing a deep learning model to detect anomalies in medical images. The team will experiment with large image datasets and then deploy the model for real-time inference on edge devices in clinics. The project has a limited budget for cloud GPU usage. Which hardware strategy best balances experimentation needs with deployment constraints?
Select an answer first - 23
A retail company is planning an AI project to forecast store-level inventory demand. The team will need to clean and integrate data from multiple legacy systems, build and tune forecasting models, and deploy the models to a cloud platform. The company has a small in-house data team with strong statistical skills but no experience with modern ML frameworks or cloud deployment. Which combination of roles and skills should the project manager prioritize when staffing the project?
Select an answer first - 24
A bank is launching an AI project to detect fraudulent transactions. The project requires expertise in fraud domain, machine learning, and real-time data processing. The bank has a strong IT team but no data scientists. The project has a tight deadline and a limited budget for external hires. Which approach best addresses the skill gaps while managing cost and timeline?
Select an answer first - 25
A project manager is allocating budget across project phases. Which phase typically requires the most data engineering effort and thus a larger allocation of personnel?
Select an answer first