Part of the Identify Business Needs and Solutions domain, which accounts for 26% of the PMI-CPMAI exam. PMI does not publish an official question count, but from its 160-minute exam (~65–105 total, ~17–27 in this domain), expect 2–3 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
9concepts
26%of the exam
Questions 16–20
- 16
An AI project team is being formed to develop a predictive maintenance system. The project requires building and training machine learning models, deploying them to production, and managing the project. Which set of roles is most appropriate for this team?
Select an answer first - 17
A project manager is creating a timeline for an AI project that involves a contractor who is only available for the first four weeks. The project has three phases: data collection, model development, and deployment. The contractor is needed for model development, which requires the data collection to be complete. The deployment phase can be done by internal staff. What is the most critical scheduling constraint?
Select an answer first - 18
A financial services firm is starting an AI project to automate document processing. The project requires a commercial ML platform for building and deploying models, as well as a data labeling service to annotate thousands of documents. The firm's procurement department is unfamiliar with AI-specific tools. What is the most effective way for the project manager to coordinate with procurement?
Select an answer first - 19
An AI project team is evaluating hardware for a project that will train a model on a large dataset. Which hardware specification is most important to consider for the training phase?
Select an answer first - 20
A project manager is developing a timeline for an AI project. The data preparation phase depends on the availability of a data engineer who is currently assigned to another project for the next three weeks. The model training phase cannot start until data preparation is complete. What is the most important consideration when sequencing these tasks?
Select an answer first