Manage the Claims Process PMI-CP Practice Questions (Page 3)

Part of the Contracts Management domain, which accounts for 50% of the PMI-CP exam.

31questions here
7free pages
8concepts
50%of the exam

Questions 11–15

  1. 11expert · hard · select all that apply

    A project team is using a risk management framework to reduce the likelihood of claims on a design-build project. They have identified a risk of claims due to unclear performance specifications. Which of the following risk responses would be effective in reducing the likelihood of claims? (Select all that apply.)

    Select an answer first
  2. 12application · medium

    A contractor submits a notice of a potential claim for additional payment due to an alleged differing site condition. The contract requires the contractor to provide notice within 14 days of discovering the condition. The contractor discovered the condition 10 days ago but has not yet submitted a formal claim. The project manager wants to resolve the issue without escalating to a formal dispute. What should the project manager do first?

    Select an answer first
  3. 13application · medium

    During a design-build project, the owner requests a change to the exterior cladding material. The contractor agrees to the change and provides a price adjustment. The parties sign a document reflecting the new scope and price. Later, the contractor submits a claim for additional costs related to a delay caused by the material change. How should the project manager classify the signed document for the cladding change?

    Select an answer first
  4. 14application · medium

    A project has a history of disputes between the owner and contractor over change requests. The project manager wants to implement a preventive measure to reduce the frequency of disputes. Which measure would be most effective?

    Select an answer first
  5. 15foundation · easy

    A project manager is reviewing lessons learned from previous projects to identify areas that frequently lead to claims. Which activity best aligns with this objective?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.