Manage the Claims Process PMI-CP Practice Questions (Page 2)
Part of the Contracts Management domain, which accounts for 50% of the PMI-CP exam.
31questions here
7free pages
8concepts
50%of the exam
Questions 6–10
- 6
A construction firm is analyzing lessons learned from past projects to identify areas that lead to claims. The analysis reveals that most claims arise from ambiguous specifications and poor site investigation. The firm wants to use this analysis to improve future projects. Which action would be most effective?
Select an answer first - 7
Which scenario is most likely to trigger a claim rather than a change order?
Select an answer first - 8
A contractor has submitted a claim for additional payment due to an owner-caused delay. The project manager believes the claim has merit but wants to resolve it quickly to avoid project disruption. The contract allows for negotiation and mediation. What should the project manager do to achieve early resolution?
Select an answer first - 9
Which practice is most effective in preventing claims and disputes on a construction project?
Select an answer first - 10
A project manager is analyzing a series of claims from a completed project. The claims all relate to delays in obtaining permits from local authorities. The project manager wants to identify the root cause to prevent similar claims on future projects. Which approach would best determine the root cause?
Select an answer first