PMIConstruction Professional (PMI-CP)
Domain 4Objective 3
Leverage Scope Governance Structures to Protect Project Scope and Foster Efficient Decision Making PMI-CP Practice Questions (Page 5)
Part of the Project Governance domain, which accounts for 5% of the PMI-CP exam.
23questions here
5free pages
3concepts
5%of the exam
Questions 21–23
- 21
A project's steering committee meets monthly, but a critical scope change request requires a decision within three days to avoid a major schedule delay. The change control board (CCB) is a subset of the steering committee and is scheduled to meet next week. What is the most effective way to facilitate a timely decision?
Select an answer first - 22
Which governance mechanism is most effective in preventing unauthorized scope changes during project execution?
Select an answer first - 23
A project manager discovers that a key stakeholder has been directing team members to add new reporting features without going through the change control process. The project is mid-execution and the stakeholder is influential but not on the change control board. What should the project manager do first to protect scope integrity?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-CP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CP” is a trademark of its owner, used for identification only.