Leverage Scope Governance Structures to Protect Project Scope and Foster Efficient Decision Making PMI-CP Practice Questions (Page 5)

Part of the Project Governance domain, which accounts for 5% of the PMI-CP exam.

23questions here
5free pages
3concepts
5%of the exam

Questions 21–23

  1. 21application · medium

    A project's steering committee meets monthly, but a critical scope change request requires a decision within three days to avoid a major schedule delay. The change control board (CCB) is a subset of the steering committee and is scheduled to meet next week. What is the most effective way to facilitate a timely decision?

    Select an answer first
  2. 22foundation · easy

    Which governance mechanism is most effective in preventing unauthorized scope changes during project execution?

    Select an answer first
  3. 23application · medium

    A project manager discovers that a key stakeholder has been directing team members to add new reporting features without going through the change control process. The project is mid-execution and the stakeholder is influential but not on the change control board. What should the project manager do first to protect scope integrity?

    Select an answer first
Finished these 3 questions?

Review the revealed explanations, or continue through the curriculum.