Leverage Scope Governance Structures to Protect Project Scope and Foster Efficient Decision Making PMI-CP Practice Questions (Page 1)

Part of the Project Governance domain, which accounts for 5% of the PMI-CP exam.

23questions here
5free pages
3concepts
5%of the exam

Questions 1–5

  1. 1application · medium

    A project is being planned, and the project manager wants to ensure that scope changes are handled consistently and efficiently. The organization has a project management office (PMO) that provides governance templates and processes. What should the project manager do to leverage this structure?

    Select an answer first
  2. 2foundation · easy

    Which formal structure is typically responsible for reviewing and approving or rejecting proposed changes to the project scope?

    Select an answer first
  3. 3application · medium

    A project manager is working in an organization where the change control board (CCB) only meets once a month. A scope change request has been submitted, but the project cannot wait a month for a decision because it would cause a critical delay. What is the best way to handle this situation?

    Select an answer first
  4. 4application · medium

    A project has a change control board (CCB) that includes representatives from multiple departments. The CCB has been unable to reach consensus on a critical scope change, causing a two-week delay. The project is time-sensitive. What should the project manager do to facilitate a decision?

    Select an answer first
  5. 5expert · hard

    A project manager is managing a project where the scope baseline is approved, but a key stakeholder is pressuring the team to add features without going through change control. The stakeholder has significant influence and could derail the project if they feel ignored. The project manager wants to protect scope while maintaining stakeholder relationships. What is the best approach?

    Select an answer first