  1. 6expert · hard

    A project manager is assigned to a project in an organization that has a steering committee but no formal change control board. The project is complex and likely to have many scope changes. The project manager wants to establish an efficient scope governance process. What should the project manager do first?

    Select an answer first
  2. 7expert · hard

    A project manager discovers that a team member has been implementing scope changes without approval, believing they are improvements. The changes have already been integrated into the product, and reversing them would cause rework and delay. The project is under a fixed-price contract. What should the project manager do to protect scope integrity and manage the situation?

    Select an answer first
  3. 8application · medium

    During a project, a senior executive informally requests a significant scope addition during a hallway conversation. The executive is not a member of the change control board. The project manager knows the addition would require additional budget and time. What should the project manager do?

    Select an answer first
  4. 9application · medium

    A project manager notices that a team lead has been informally agreeing to add small enhancements for a business unit, believing these are too minor to require formal change control. The project is on a fixed-price contract. What should the project manager do to protect the project scope?

    Select an answer first
  5. 10application · medium

    A project is being initiated in an organization that has a well-defined governance framework. The project manager needs to ensure that scope decisions are made efficiently and consistently. Which action best leverages the existing governance structures?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CP” is a trademark of its owner, used for identification only.