Part of the Domain 3 Product domain, which accounts for 19% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~13–23 in this domain), expect 3–6 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)
18questions here
4free pages
4concepts
19%of the exam
Questions 16–18
- 16
A team has a large backlog item that describes a broad capability. To make it ready for an upcoming iteration, the team needs to break it down. What is the result of this decomposition?
Select an answer first - 17
A product owner is prioritizing the backlog for a release that must meet a tight deadline. The stakeholders have identified several features, but the team is concerned that some features are too large to fit into the release. The product owner needs to prioritize the features and ensure the team can deliver them. What should the product owner do?
Select an answer first - 18
During backlog refinement, the team identifies a user story that is still too large to be completed in one iteration. What should the team do to make it actionable?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-ACP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-ACP” is a trademark of its owner, used for identification only.